Projects Under Construction

Road/Drainage Projects

Project No. Project Name Contract Amount Contractor
21-08-01 Thomas Avenue Trench Drain Replacement Project $54,656.00 Deig Brothers
21-08-02 House House #1 Parking Lot Drainage  $36,280.00 Ragle Construction 

PAVING PROJECTS 

 Project No. Project Name Contract Amount Contractor

Sidewalks and Curb Ramps

Project No. Project Name Contract Amount Contractor

Federal Aid Project - 80% Federally Funded

Project Name Contract Amount Contractor
   
Covert Avenue (US 41 - Newburgh Road)
$5,995,580
JBI Construction
   

** Please see the below the estimated Walnut Street Construction timeline:

  • PHASE 1:  US 41 to Weinbach Avenue
    • Construction is complete.  Punch List Items being addressed. 
  • PHASE 2:  Weinbach to Vann Avenue
    • Right-of-way Staking in place
    • Right-of-way Acquisition ongoing
    • Construction Letting scheduled for October 14, 2021
  • Phase 3:  US 41 to Martin Luther King Jr. Boulevard
    • Design and Environmental studies ongoing
    • Public Hearing anticipated in early 2021