Click here to be directed to an interactive map of current projects (Beta Version).
Road/Drainage Projects
|
Project Number |
Project Name |
Contract Amount |
Contractor |
Complete |
Expected Completion Date |
22-11-01 |
96" Storm Sewer Repairs - Southeast side |
$3,427,919.00 |
Culy Contracting LLC |
95% |
|
23-004 |
2023 Dresden Street Outfall Repairs |
$816,800.00 |
Blankenberger Bros |
0% |
|
23-024 |
Evansville East Side Drainage Project Phase 1 |
$2,713,063.00 |
Blankenberger Brothers Inc |
40% |
|
25-008 |
First Ave Storm Sewer Replacement |
$280,800.00 |
Blankenberger Brothers Inc |
0% |
|
Paving Projects
|
Project No. |
Project Name |
Contract Amount |
Contractor |
Complete |
Expected Completion Date |
24-012 |
Cross Pointe Blvd and Indiana St Roundabout |
$2,504,990.62 |
JBI Construction |
0% |
|
25-001 |
2025 Mill and Overlay - Phase 1 |
$1,430,831.38 |
E&B Paving LLC |
85% |
|
25-002 |
2025 Mill and Overlay - Phase 2 |
$2,648,270.95 |
E&B Paving LLC |
70% |
|
Sidewalks and Curb Ramps
|
Project No |
Project Name |
Contract Amount |
Contractor |
Complete |
Expected Completion Date |
24-009 |
2024 ADA Curb Ramp Improvements |
$168,891.90 |
River Town Construction LLC |
95% |
|
Federal Aid Project - 80% Federally Funded
|
Project Name |
Construction Inspector |
Contractor |
Complete |
Expected Completion Date |
Walnut 3 |
Structurepoint |
Blankenberger Brothers |
95% |
September 2025 |
** Please see the below the estimated Walnut Street Construction timeline:
- PHASE 1: US 41 to Weinbach Avenue
Construction is complete.
- PHASE 2: Weinbach to Vann Avenue
Construction is ongoing. Expected Completion by the end of 2023
- Phase 3: US 41 to Martin Luther King Jr. Boulevard
Project has been bid and awarded to Blankenberger
- Phase I at US 41 will start by the end of July 2023.
Utility relocations have begun.